The proposed delivery programs for the various components of the site are outlined below:

565 Hay Street
Development Approval received
23 September 2011
Demolition of Law Chambers
August 2012
Works commence on site
April 2013
Completion
June 2014

 

Treasury Buildings
Design commencement
2008
DA Approval received
October 2011
Works commence on site
August 2012
Completion
Early 2015

 

City of Perth Library
Council Decision to Proceed
July 2010
Tenders for Architect Called
May 2011
Winning Scheme Confirmed
August 2011
Commence Construction
April 2013
Completion
September 2014

 

Office Tower
DA Approval received
October 2011
Commence Construction
August 2012
Completion
Early 2015

 

St Georges Plaza
Works commence on site
April 2013
Upgrade works completed
Late 2014

 

Public Trustee Building
Minor upgrade works were completed
Early in 2012